Arihant Expert Team Solutions for Exercise 2: PRACTICE QUESTIONS for Phase I

Author:Arihant Expert Team

Arihant Expert Team Quantitative Aptitude, English, Reasoning, General Knowledge/ General Awareness Solutions for Exercise - Arihant Expert Team Solutions for Exercise 2: PRACTICE QUESTIONS for Phase I

Attempt the free practice questions from Exercise 2: PRACTICE QUESTIONS for Phase I with hints and solutions to strengthen your understanding. Study Guide SBI PO Preliminary Examination 2019 solutions are prepared by Experienced Embibe Experts.

Questions from Arihant Expert Team Solutions for Exercise 2: PRACTICE QUESTIONS for Phase I with Hints & Solutions

EASY
SBI PO Mains
IMPORTANT

3 men can do a piece of work in 12 days, 5 women in 8 days and 20 children in 3 days. In how many days can a man, a woman and a child working together complete the piece of work?

EASY
SBI PO Mains
IMPORTANT

A certain number of men can complete a piece of work in 40 days. If there were 8 men more the work could be finished in 10 days less. How many men were there afterwards?

EASY
SBI PO Mains
IMPORTANT

A certain number of men can complete a piece of work in 90 days. If there are 8 men less, it would take 10 days more. How many men were there originally?

EASY
SBI PO Mains
IMPORTANT

A and B complete a piece of work in 5 days working together. If A had worked twice as fast the work would have been completed in 4 days. In how many days can A alone complete the work?

MEDIUM
SBI PO Mains
IMPORTANT

Two men alone or three women alone can complete piece of work in 4 days. In how many days can one woman and one man together complete the same piece of work?

EASY
SBI PO Mains
IMPORTANT

A water tank has three taps A, B and C. Tap A, when opened, can fill the water tank alone in 4 h. Tap B, can fill the water tank alone in 6 h and tap C can empty the water tank alone in 3 h. If taps A, B and C are opened simultaneously. How long will it take to fill the tank completely?

EASY
SBI PO Mains
IMPORTANT

8 men can complete a piece of work in 20 days. 8 women can complete the same work in 32 days. In how many days will 5 men and 8 women together complete the same work.

MEDIUM
SBI PO Mains
IMPORTANT

6 men can complete a piece of work in 12 days. 8 women can do the same piece of work in 18 days where as 18 children can complete in 10 days. 4 men, 12 women and 20 children work together for 2 days. If only men were to complete the remaining work in 1 day, how many men would be required totally?