Embibe Experts Solutions for Chapter: Arithmetic, Exercise 12: Exercise 12

Author:Embibe Experts

Embibe Experts Quantitative Aptitude Solutions for Exercise - Embibe Experts Solutions for Chapter: Arithmetic, Exercise 12: Exercise 12

Attempt the free practice questions on Chapter 1: Arithmetic, Exercise 12: Exercise 12 with hints and solutions to strengthen your understanding. Embibe Quantitative Aptitude solutions are prepared by Experienced Embibe Experts.

Questions from Embibe Experts Solutions for Chapter: Arithmetic, Exercise 12: Exercise 12 with Hints & Solutions

MEDIUM
SSC CGL Tier 1
IMPORTANT

A can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave the work. Then C alone finishes the remaining work in 10 days. In how many days will C finish the full work?

EASY
SSC CGL Tier 1
IMPORTANT

Ten women can do a work in six days. Six men can complete the same work in five days. What is the ratio between the capacity of a man and a woman?

MEDIUM
SSC CGL Tier 1
IMPORTANT

X can do a piece of work in 20 days and Y can do the same work in 30 days. They finished the work with the help of Z in 8 days. If they earned a total of Rs. 5550, then what is the share of Z?

EASY
SSC CGL Tier 1
IMPORTANT

A,B and C and do a piece of work in 20 days, 30 days and 60 days respectively. A is helped by B and C every third day. In how many days will the work be completed -

EASY
SSC CGL Tier 1
IMPORTANT

A and B can do work in 12 days, B and C in 15 days, and C and A in 20 days. They all work together for 6 days and then A left.In how many more days can B and C finish the remaining work?

MEDIUM
SSC CGL Tier 1
IMPORTANT

15 men take 21 days of 8 hours each to do a piece of work. How many days of 6 hours each would 21 women take, if 3 women do as much work as 2 men?

HARD
SSC CGL Tier 1
IMPORTANT

A,B and C can do a piece of work individually in 8,12 and 15 days respectively. Aand B start working together but A quits after working for 2 days. After this, C joins and works till completion of the work. In how many days will the work be completed?

HARD
SSC CGL Tier 1
IMPORTANT

A contractor engaged 100 labourers for construction work to be completed in 96 days. But only 17th of the work was done in 16th of the scheduled time. The additional number of labourers that will be required to complete the work in time is: