A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved
(a)26, 000 m3
(b)26, 500 m3
(c)27, 000 m3
(d)27, 500 m3

50% studentsanswered this correctly