If 5 men or 9 women can finish a piece of work in 19 days, 3 men and 6 women will do the same work in:

50% studentsanswered this correctly

Important Questions on Time and Work

EASY
RBI Grade B Phase - I
IMPORTANT
A can do a piece of work in 12 daysB is 60% more efficient than A. The number of days, taken by B to do the same piece of work, is:
EASY
RBI Grade B Phase - I
IMPORTANT
A and B can do a piece of work in 45 and 40 days, respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave?