If A can complete a work in 30 days and B can complete the same work in 25 days, then in how many days will 'A' and 'B' together complete the work?

50% studentsanswered this correctly

Important Questions on Numerical Ability

EASY
SSC
IMPORTANT
If 100 men can do 100 jobs in 100 days, then 1 man can do one job in:
EASY
SSC
IMPORTANT
Ajit can complete a job in 4 days, Manoj can complete the same job in 6 days and Ravi can complete it in 12 days. In how many days will Ajit, Manoj and Ravi together complete the same job?
EASY
SSC
IMPORTANT
A and B can finish a work in 16 days while A alone can do the same work in 24 days. Therefore, B alone can finish the same work in _____ days.
EASY
SSC
IMPORTANT
A, B and C undertake to complete a piece of work for Rs.1950. A works for 8 days, B for 9 days and C for 12 days to complete the work. If their daily wages are in the ratio of 3 : 5 : 4, what does C get?
EASY
SSC
IMPORTANT
Two taps A and B can fill a cistern in 30 minute and 45 minute respectively. There is third exhaust tap C at the bottom of the tank. If all the taps are opened at the same time the cistern will be full in 45 minute. In what time can exhaust tap C empty the cistern when full?
EASY
SSC
IMPORTANT
Two taps A and B can separately fill a cistern in 24 minutes and 30 minutes respectively. Both the pipes are opened together. Find when the pipe B must be turned off so that the cistern may be full in 18 minutes.
EASY
SSC
IMPORTANT
Efficiency of B is 80% of A. If both can complete a work in 24 days, in how many days B alone will complete the same work?
EASY
SSC
IMPORTANT
The efficiency of A is twice that of B. A completes a work in 9 days less than taken by B. In how many days A alone will complete this work?