To complete a task in 45 days, a contractor employees 45 people. Upon reviewing the work after 30 days, he notices that only half the task is complete. In order to meet the deadline of 45 days, how many extra people must he employ?

50% studentsanswered this correctly

Important Questions on Time and Work, Pipe and Cistern

MEDIUM
IBPS RRB Office Assistant Mains
IMPORTANT
If 15 men or 24 women or 36 boys can do a piece of work in 12 days working 8 hours a day, how many men must be associated with 12 women and 6 boys to do another piece of work 94 times as great in 30 days working 6 hrs./ day?
EASY
IBPS RRB Office Assistant Mains
IMPORTANT
A can build a wall in 30 days. B can demolish that wall in 60 days. If A and B work on alternate days, when will the wall be completed?
MEDIUM
IBPS RRB Office Assistant Mains
IMPORTANT
To do a certain piece of work B would take three times as long as A and C together and C twice as long as A and B together. The three men by their united exertions can complete the work in 10 days. How long would B take by himself?
EASY
IBPS RRB Office Assistant Mains
IMPORTANT
If 3 men or 4 women can reap a field in 43 days, how long will 7 men and 5 women take to reap it?
MEDIUM
IBPS RRB Office Assistant Mains
IMPORTANT
25 men can reap a field in 20 days. When should 15 men leave the work, if the field is to be reaped in 37.5 days after they leave the work?
MEDIUM
IBPS RRB Office Assistant Mains
IMPORTANT
A, B and C can do a piece of work in 6, 12 and 24 days, respectively. In how many days will they altogether do it?
EASY
IBPS RRB Office Assistant Mains
IMPORTANT
A and B can finish a piece of work in 30 days, B and C in 40 days while C and A in  60 days. How long will they take to finish it together?
EASY
IBPS RRB Office Assistant Mains
IMPORTANT
B can do a piece of work in 6 hours, B and C can do it in 4 hours and A, B and C in 83 hours. In how many hours can A and B do it?