IBPS RRB Office Assistant Mains
IMPORTANT
Earn 100

To complete a task in days, a contractor employees people. Upon reviewing the work after days, he notices that only half the task is complete. In order to meet the deadline of days, how many extra people must he employ?
(a)
(b)
(c)
(d)

50% studentsanswered this correctly

Important Questions on Time and Work, Pipe and Cistern
MEDIUM
IBPS RRB Office Assistant Mains
IMPORTANT
If men or women or boys can do a piece of work in days working hours a day, how many men must be associated with women and boys to do another piece of work times as great in days working hrs./ day?

EASY
IBPS RRB Office Assistant Mains
IMPORTANT
A can build a wall in days. B can demolish that wall in days. If A and B work on alternate days, when will the wall be completed?

MEDIUM
IBPS RRB Office Assistant Mains
IMPORTANT
To do a certain piece of work would take three times as long as and together and twice as long as and together. The three men by their united exertions can complete the work in days. How long would take by himself?

EASY
IBPS RRB Office Assistant Mains
IMPORTANT
If men or women can reap a field in days, how long will men and women take to reap it?

MEDIUM
IBPS RRB Office Assistant Mains
IMPORTANT
men can reap a field in days. When should men leave the work, if the field is to be reaped in days after they leave the work?

MEDIUM
IBPS RRB Office Assistant Mains
IMPORTANT
A, B and C can do a piece of work in and days, respectively. In how many days will they altogether do it?

EASY
IBPS RRB Office Assistant Mains
IMPORTANT
A and B can finish a piece of work in days, B and C in days while C and A in days. How long will they take to finish it together?

EASY
IBPS RRB Office Assistant Mains
IMPORTANT
B can do a piece of work in hours, B and C can do it in hours and A, B and C in hours. In how many hours can A and B do it?