EASY
Earn 100

To complete a task in days, a contractor employees people. Upon reviewing the work after days, he notices that only half the task is complete. In order to meet the deadline of days, how many extra people must he employ?

50% studentsanswered this correctly
Important Questions on Time and Work
HARD

HARD

MEDIUM

MEDIUM
Marc and Mike together can build a 5 foot high wall in 10 days. If Marc alone can build the same wall in 12 days, in how many days will Mike alone build the same wall?
(A) 50 days
(B) 60 days
(C) 20 days
(D) 24 days