West Bengal Board Solutions for Chapter: Time and Work, Exercise 3: Let's Work out - 17.1

Author:West Bengal Board

West Bengal Board Mathematics Solutions for Exercise - West Bengal Board Solutions for Chapter: Time and Work, Exercise 3: Let's Work out - 17.1

Attempt the practice questions on Chapter 17: Time and Work, Exercise 3: Let's Work out - 17.1 with hints and solutions to strengthen your understanding. Ganitprabha (MATHEMATICS TEXT BOOK) Class 8 solutions are prepared by Experienced Embibe Experts.

Questions from West Bengal Board Solutions for Chapter: Time and Work, Exercise 3: Let's Work out - 17.1 with Hints & Solutions

EASY
8th West Bengal Board
IMPORTANT

Time (In days) Amount of work (in length)
25 45
15 ?

Let's make a story of mathematics and find out the relation seeing the above chart.

MEDIUM
8th West Bengal Board
IMPORTANT

We can see after 15 days of digging a canal of 1200 meter length, 34 part of the canal have been dug. Let's calculate how many days will be needed to dig the rest part.

MEDIUM
8th West Bengal Board
IMPORTANT

3 tractors can plough 18 bighas in a day. If k bighas can be ploughed by 7 tractors in a day the find k.

EASY
8th West Bengal Board
IMPORTANT

In Kusum's factory 35 men can cast 10 ton iron part in a week. The owner has got an order of casting 14 ton iron parts in a week. Let's find out the proportion and calculate how many new men will be needed.

EASY
8th West Bengal Board
IMPORTANT

Number of men Amount of week (In a number of cycles)
9 6
72 ?

Let's make the story in mathematical language and find out the relation seeing the above chart.

MEDIUM
8th West Bengal Board
IMPORTANT

A pond will be dug in our locality. 24 men need 12 days to cut that pond. Let's find out the proportion and find relation how many men will be needed to dig that pond in 8 days.

MEDIUM
8th West Bengal Board
IMPORTANT

45 members in a bulb manufacturing co-operative factory can make 10000 bulbs in 12 days. Based on a sudden order 10000 bulb have to be made in 9 days. Let's calculate how many extra members need to be appointed to supply the bulbs according to the agreement.

MEDIUM
8th West Bengal Board
IMPORTANT

250 men need 18 days to dig a pond of 50 metre length and 35 metre breadth. Let's calculate how many days will be needed by 300 men to dig a pond 70 metre length and 40 metre breadth of the same depth.