To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in 1113 days, then find the time taken by B alone can complete 79 part of the original work.

50% studentsanswered this correctly

Important Questions on Arithmetic

MEDIUM
SSC CGL Tier 1
IMPORTANT
Samir and Puneet can complete the same work in 10 days and 15 days respectively. The work was assigned for 4500. After working together for 3 days Samir and Puneet involved Ashok. The work was completed in total 5 days. What amount (in ) was paid to Ashok?
MEDIUM
SSC CGL Tier 1
IMPORTANT
A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 4 days, B had to leave. Then A working with a new worker C completed the remaining work in 3 days. If C works alone, in how many days he can do 40% of the same work?
MEDIUM
SSC CGL Tier 1
IMPORTANT
Each one of five men independently can complete a work in 20 days. The work is started by one person. The next day one more person joins and every next day one more person joins. From the fifth day, five persons continued working as a team. In how many days, will the work be completed?
MEDIUM
SSC CGL Tier 1
IMPORTANT
A and B together can complete a certain work in 20 days whereas B and C together can complete it in 24 days. If A is twice as good a workman as C, then in what time will B alone do 40% of the same work?
MEDIUM
SSC CGL Tier 1
IMPORTANT
A can complete a work in 60 days. B is 25% more efficient than A. They work together for 15 days. C alone completes the remaining work in 14 days. Find the time required by B and C together will complete 58th part of the original work.
MEDIUM
SSC CGL Tier 1
IMPORTANT
Fourteen persons can do a work in 18 days. After 5 days of work, 6 workers left the work, and joined back on the last day of the work. In how many days the work got completed?
MEDIUM
SSC CGL Tier 1
IMPORTANT
Eighteen men can complete a work in14  days. Three women do as much as work as two men.  Five men and six women started the work and continued for 4 days. Subsequently 3 more men joined the group.In how many total days was the work completed?
MEDIUM
SSC CGL Tier 1
IMPORTANT
A can do a piece of work in 2 days, and B can do five times the same work in 15 days when they work for ten hours a day. If they work together, then how many hours in addition to a days work will they require to complete the work?